B2Gold 2021 eye on higher production guideline

For 2021, B2Gold remains well positioned for continued strong operational and financial performance with total production guidance of between 970,000 - 1,030,000 ounces of gold (including attributable ounces projected from Calibre of between 50,000 - 60,000 ounces) with total consolidated forecast cash operating costs of between $500 - $540 per ounce and total consolidated AISC of between $870 - $910 per ounce.

Consolidated cash operating costs and AISC per ounce are forecast to be higher than 2020, mainly due to the planned lower production and higher planned stripping activities at Fekola, higher forecast fuel and labour costs in Mali, and the drawdown of ore stockpiles at Otjikoto.

Due to open pit mine sequencing, consolidated gold production is expected to be significantly weighted to the second half of 2021; for the first half of 2021, consolidated gold production is forecasted to be between 365,000 – 385,000 ounces, which is expected to increase significantly to between 555,000 – 585,000 ounces during the second half of 2021.

Based on current operating plans, over a five-year outlook from 2020 to 2024, annual consolidated gold production is forecast to average 950,000 ounces with AISC averaging $825 per ounce. The results of the Gramalote Feasibility Study are expected to be announced in April 2021, with a construction decision expected to be made shortly thereafter.

The Company is re-evaluating the Kiaka Project in Burkina Faso, and expects to have an updated economic assessment of the project for internal review completed by the end of the first quarter of 2021, followed by an updated feasibility study by mid-year 2021.

Following a very successful year for exploration in 2020, B2Gold is planning a year of aggressive exploration in 2021 with a budget of approximately $66 million (excluding Gramalote), including a record $25 million allocated to the Company's ongoing grassroots exploration programs.

An updated mineral resource estimate for the Anaconda area (located 20 kilometres north of Fekola), based on the completed 2020 drill program, is expected in the first quarter of 2021 and the Company has allocated $8 million for drilling to expand the mineral resource estimate in 2021; in addition an initial mineral resource estimate is expected to be completed for the Cardinal zone (located within 500 metres of the current Fekola resource pit) in the first quarter of 2021.

Based on current assumptions, including a gold price of $1,800 per ounce, the Company expects to generate cashflow from operating activities of approximately $630 million in 2021. Despite some of the challenges that the current Covid-19 pandemic has created worldwide and in each of the locations where the Company operates or is head-quartered, the Company continues to operate virtually unimpeded.

The B2Gold executive team is very proud of the Company's employees' dedication and resilience in these challenging times and believe it is in part due to the executive team's and mine employees' years of experience in all aspects of international mining, and the Company's culture of treating all its stakeholders with fairness, respect and transparency. This successful approach is reflected again in the Company's record performance in 2020.

The Company continues to address the Covid-19 pandemic and minimize its potential impact at B2Gold's operations. B2Gold places the safety and well-being of its workforce and all stakeholders as its highest priority and continues to encourage input from all its stakeholders as the Covid-19 situation evolves.

The Company continues to implement measures and precautionary steps to manage and respond to the risks associated with Covid-19 to ensure the safety of B2Gold's employees, contractors, suppliers and surrounding communities where the Company works while continuing to operate. The Company is continually updating these plans and response measures based on the safety and well-being of its workforce, the severity of the pandemic in areas where it operates, global response measures, government restrictions and extensive community consultation.

The Company is working closely with national and local authorities and continues to closely monitor each site's situation, including public and employee sentiment to ensure that stakeholders are in alignment with continued safe operation of its mines.

 